§ 5-5. Permit fees.  


Latest version.
  • That on all buildings, structures or alterations requiring a building permit, as set forth in the International Building Code, Section 105, Permits, fees shall be paid as required at the time of filing application, as set forth in Section 108, Fees, in accordance with Schedule A [below].

    City of Athens Development Permit Fee Chart
    SCHEDULE A

    Type of Permit
    Residential one trade permits
          Plumbing $ 80.00
          Electrical $ 80.00
          Mechanical (HVAC) $ 80.00
          Fence $ 80.00
          Irrigation $ 80.00
    Residential Accessory Building (Includes slab, but no electric, plumbing or mechanical)
          Accessory Building Permit Fee $ 80.00
          Plan Review Fee included
          TOTAL $ 80.00
    Residential - Valuation $100 to ≤ $40,000.00 (Roughly equates to 400 SF)
          Building Permit Fee $ 350.00
          Plan Review Fee included
          Plumbing Fee included
          Mechanical Fee included
          Electrical Fee included
    Includes in-ground pools       TOTAL $ 350.00
    Residential New - Valuation ≥ $40,000 to $125,000.00 (Roughly equates to 2,000 SF)
          Building Permit Fee $ 775.00
          Plan Review Fee included
          Mechanical Fee included
          Electrical Fee included
          Plumbing Fee included
    Includes in-ground pools       TOTAL $ 775.00
    Residential New - Valuation ≥ $125,000.00 to ≤ $225,000 (Roughly equates to 3,500 SF)
          Building Permit Fee $ 1,150.00
          Plan Review Fee included
          Mechanical Fee included
          Electrical Fee included
          Plumbing Fee included
          TOTAL $ 1,150.00
    Values less than $100 do not require a permit.
    Commercial Remodel - Valuation: ≤ $25,000 (Roughly equates to 500 SF)
          Building Permit Fee $ 250.00
          Plan Review Fee included
          Mechanical Fee $ included
          Electrical Fee $ included
          Plumbing Fee $ included
    * Individual trade permits are $80.00 apiece
    $ 250.00
    Commercial Remodel ≥ $25,000 to ≤ $50,000 (Roughly equates to 1,000 SF)
          Building Permit Fee $ 605.00
          Plan Review Fee $ included
          Mechanical Fee $ included
          Electrical Fee $ included
          Plumbing Fee $ included
    * Individual trade permits are $80.00 apiece
    $ 605.00
    Commercial Addition - Valuation ≥ $50,000 to ≤ $250,000 (Roughly equates to 3,000 SF)
          Building Permit Fee $ 2,000.00
          Plan Review Fee included
          Mechanical Fee included
          Electrical Fee included
          Plumbing Fee included
    *
    $ 2,000.00
    Commercial New Valuation ≥ $250,000 to ≤ $6,000,000 (Roughly equates to 7,500 SF)
          Building Permit Fee $ 4,075.00
          Plan Review Fee included
          Mechanical Fee included
          Electrical Fee included
          Plumbing Fee included
          TOTAL $ 4,075.00
    Reinspection Fees
          1st Reinspection Fee no charge
          2nd Reinspection Fee $ 80.00
    Certificate of Occupancy
    $ 100.00
    Demolition
    $ 40.00
    Carport
    $ 20.00
    Canopy or Tent
    $ 20.00
    Gas Line Repair
    $ 80.00
    Sign Permit
    $ 20.00
    Tree Removal
    $ 20.00
    Curb Cut
    $ 40.00
    House Moving
    $ 200.00
    Driveway/Patio
    $ 20.00
    CONTRACTORS REGISTRATION FEES
    Contractor/General
    $ 60.00
    Mechanical
    $ 30.00
    Plumbing Master
    $ 30.00
    Irrigator
    $ 30.00
    Backflow Inspectors
    $ 30.00

     

    FIRE FEES

    Open Burning (10'x10'x4') $ 20.00
    Open Burning (30'x30'x10') $ 50.00
    Open Burn 20 Acres plus (Annual Permit) $ 300.00
    Fire Works Stand (per stand) $ 50.00
    Carnivals and Fairs $ 65.00
    Fire Alarm System in Comml. Bldg. $100.00 1st 25 devices, then $0.25 per additional device
    Kitchen Hood System $ 65.00
    Overhead Sprinkler System $100.00 1st 25 heads, then $0.25 per additional head
    Underground Fire Service Mains $ 65.00

     

    A-6 SCHEDULE OF FEES

    ZONING
    APPLICATIONS

    0—5 Acres 5—20 Acres Over 20 acres
    Zoning Change or Text Amendment $300.00 +
    $20.00
    per acre
    $400.00 +
    $20.00
    acre
    $500.00 +
    $20.00
    per acre
    Plan Development with site plan $400.00 +
    $20.00
    per acre
    $500.00 +
    $20.00
    acre
    $600.00 +
    $20.00
    per acre
    Amended Site Plan $150.00 $200.00 $250.00
    Specific Use Permit $100.00 $100.00 $100.00
    Temporary Use Permit $40.00 $40.00 $40.00
    Board of Adjustment $250.00 $250.00 $250.00
    Zoning Verification Letter $20.00 per letter $20.00 per letter $20.00 per letter

     

    PLATTING APPLICATIONS 0—5 Acre 5—20 Acre Over 20 acres
    Preliminary Plat Res/Comm'l $150.00 + $10.00 per lot $200.00 + $10.00 per lot $250.00 + $10.00 per lot
    Final Plat $150.00 + $10.00 per lot $200.00 + $10.00 per lot $250.00 + $10.00 per lot
    Development Plat, Minor Plat $100.00 + $10.00 per lot $100.00 + $10.00 per lot $100.00 + $10.00 per lot
    Replat $300.00 + $10.00 per lot $300.00 + $10.00 per lot $300.00 + $10.00 per lot
    Amended Plat $150.00 + $10.00 per lot $150.00 + $10.00 per lot $150.00 + $10.00 per lot
    Civil Construction Plans $500.00 (1st and 2nd review) & $150.00 for each additional review

     

(Ord. No. O-40-07, § 4, 10-22-07; Ord. No. O-24-16, § I.A., 6-13-16)

Editor's note

See editor's note at art. I.

Cross reference

Payment of sewer tap charge before issuance, § 21-5.